| 1. | Date of approval by Planning Commission | 29 May 1978 |
| 2. | Commencement of construction | March 1979 |
| 3. | Original Estimates | Rs. 59=14 lakhs |
| 4. | Expenditure incurred up to march 1986 | Rs. 123=59 lakhs |
| 5. | Budget allotted for this year 1986-87 | Rs. 51=50 lakhs |
| 6. | total fund provided so far | Rs. 175=09 lakhs |
| 7. | Date of constitution of Commissioning team | 16 April 1986 |
| 8. | Expected Date of Hand over of OPD, Wards Block and Main buildings | December 1986 |
| 9. | Expected date of handover of entire hospital complex by P.W.D. | March 1987 |
| 10. | Date of submission of report of 3 Sub- Committees | 30 September 1986 |
| 11. | Total beds under construction | 100 |
| 12. | Total Bed completed by 1990 | 300 |