1. Date of approval by Planning Commission 29 May 1978
2. Commencement of construction March 1979
3. Original Estimates Rs. 59=14 lakhs
4. Expenditure incurred up to march 1986 Rs. 123=59 lakhs
5. Budget allotted for this year 1986-87 Rs. 51=50 lakhs
6. total fund provided so far Rs. 175=09 lakhs
7. Date of constitution of Commissioning team 16 April 1986
8. Expected Date of Hand over of OPD, Wards Block and Main buildings December 1986
9. Expected date of handover of entire hospital complex by P.W.D. March 1987
10. Date of submission of report of 3 Sub- Committees 30 September 1986
11. Total beds under construction 100
12. Total Bed completed by 1990 300